A few weeks ago at the LA Auto Show, BMW made news by announcing a
partnership with NRG's EVgo to install an additional 500 DC Fast Charge
stations in 25 major US markets. The project is called the ChergeNow DC
Fast and is actually the second phase of a program started in 2014,
which brought 100 DC fast charge stations to select California areas. I
was there at the show for Press Preview days, and had the opportunity to
sit down with basically all of the top EV infrastructure managers at
BMW of North America. Seated at the table were Robert Healey, Electric
Vehicle Infrastructure Manager, Idine Ghoreishian, Electric Vehicle
Infrastructure Specialist, and Cliff Fietzek, Manager of Connected
eMobility.
Even though the news of the ChargeNow DC Fast program had just been
released, I wanted to first talk about the East and West Coast Express
Charging Corridors. If you remember, this program was announced back in January at NAIAS and
the press release stated that approximately 100 stations would be
installed in these corridors (Washington, DC to Boston, MA on the East
Coast, and San Diego, CA, to Portland, OR, on the West Coast) and it
would be completed by the end of 2015. This was a joint venture between
BMW, Volkswagen and ChargePoint. ChargePoint is responsible for the
installations, and BMW and VW are basically telling them where they want
them, and footing the vast majority of the bill. Time is running out
and I knew they wouldn't hit the predicted deadline, so I asked the
group what happened, and when can we expect it to be done. Here are some
quotes from the discussion:
 |
| Rob Healey, BMW's top EV infrastructure manager |
When asked about why they missed the predicted end of 2015 completion date, Fietzek said:
"The
business model for ChargePoint changed for this program. Before this
they were responding to site hosts that wanted to have a charger
installed. Basically the site host would call them, and say they wanted a
charger. Now, ChargePoint had to go out and say to property owners, 'I
need to put a charger here, because BMW and Volkswagen want me to, do
you want to work with us?' This was very different from what they were
accustomed to."
 |
50kW DC stations which are part of the
West Coast Express Charging Corridor.
Photo credit: Tony Williams |
Ghoreishian added:
"Another challenge of placement goes back to
our goal of making sure they were no more than 50 miles apart. Seventy
five miles just won't work."
I also learned that getting the sites in good locations was more
important than just getting them in the ground and meeting a deadline.
BMW knew these locations would likely be used for years to come, so it
would be worth their while to take the time to make sure they got good
locations. In that vein, Healey had this to say:
"There is a
process in place between BMW and VW; collectively we have the final
(site) approval. There were a lot of sites offered to us that we
rejected. For instance, we looked at the customer and said, 'Do you want
to have your wife go in and charge in this area late at night?' There
were sites that we rejected because we didn't think it was a safe place.
We want the best sites for our customers, basically."
I then asked if they thought BMW should finish this program before they
start new infrastructure projects, like the NRG EVgo program which had
just been announced and Fietzek quickly said:
"Different partners,
different projects. I'd rather have them running in parallel than
waiting for one to finish before starting another. We'll get things done
much faster this way."
 |
| Cliff Fietzek,
Manager of Connected eMobility for BMW of North America, stands in front
of the special edition Shadow Sport i3 on display at the LA Auto Show |
Finally, I asked that since it's clear the program won't be finished on
time, when can we expect the two Express Charging Corridors to be
completed, and Healey answered:
"Yeah, we're a little delayed.
We're now shooting for early spring for completion. We always knew it
was going to be tight. We sat with ChargePoint, we talked to the
Volkswagen people and said, 'Can we do this in one year?' We knew
approximately where we wanted to install the stations, but we still
needed to contact the property owners, sign site host agreements, go
through permitting and that just took more time than we expected. If you
look at the ramp up, we started off slow, but are now really ramping
up. We should have about 52 stations active by then end of the year,
with another 19 already under construction. We're looking at finishing
in late March or April."
Having personally gone through the process of installing a DC fast charger on my property in Montclair, NJ,
I know the challenges that can arise during the process. I'll actually
be pretty impressed if they do finish by Spring. That would mean that
they installed the 100 stations on two coasts in about 15 months, and
the company doing all of the site host agreements, permitting and
installations never really took on a project like this before. That's
really not bad in my opinion.
 |
| The DC Fast Charge Station I installed in Montclair, NJ. It's part of the East Coast Express Charging Corridor program |
With that progress update on the East and West Coast Express Charging
Corridors finished, I turned the discussion to the announcement made
just hours before, the national ChargeNow DC Fast expansion.
This is actually an expansion of a program started in 2014, when BMW
and NRG teamed up to install 100 DC Fast chargers to select California
markets. That program was completed earlier this year, and this is the
second phase. There will be an additional 500 DC Fast chargers installed
in 25 markets around the country.
When I asked about why they chose these specific markets, Healey said,
"One
of the important points of the expansion of the NRG program is that
these 25 markets cover 80% of our current i3 sales. Now, we don't want
to forget about the other 20% of our customers; we're working on it, and
you'll be hearing from us shortly about how we're filling in the other
20%. It's really a systematic approach."
The 25 markets covered in this second phase of the program are:
Atlanta, GA; Austin, TX; Boston, MA; Chicago, IL; Dallas, TX; Denver,
CO; Fresno, CA; Houston, TX; Los Angeles, CA; Miami, FL; Monterey, CA;
Nashville, TN; New York, NY; Orlando, FL; Philadelphia, PA; Phoenix, AZ;
Portland, OR; Raleigh, NC; Sacramento, CA; Salt Lake City, UT; San
Diego, CA; San Francisco, CA; Santa Barbara, CA; Seattle, WA and
Washington, DC.
Arun Banskota, President and CEO of NRG's EVgo had this to say about the program:
“It is our mission to install the right charging solutions at the
right places, and EV drivers have overwhelmingly told us they prefer DC
Fast chargers at public spaces. Over the next 24 months EVgo will add
reliable DC Fast Combo capability to what is already America’s largest
DC Fast charging network. This will be the fastest and most cost
effective build out of a new network ever – thanks in large part to our
existing infrastructure and committed retail host partners... The only way such a massive expansion is possible is because of the
purpose built, and forward looking planning behind the EVgo network...EVgo has installed infrastructure with the ability to
efficiently and economically add this new DC Fast Combo standard as the
number of electric vehicles have increased. EVgo owns and operates our
chargers with long term agreements with premium retail hosts, and is
able to provide the level of customer service, reliability, and pricing
that will lead to increased EV adoption and high satisfaction among the
existing base of EV drivers.”
The deployment rate of these 500 stations is expected to be aggressive.
NRG is a very large company with vast resources and plenty of experience
with regards to installing infrastructure. After all, they are an
electric utility company. Healey told me that they have existing sites
that currently have CHAdeMO stations that they'll be adding a Combo
(CCS) station to, as well as many other sites already identified and
ready to go. He expects to see hundreds of stations completed within the
first year and the entire 500 stations in the ground and operational by
the end of 2018. He even said that he's being conservative with these
predictions based on the lessons learned by the previous programs they
worked on, and that it is quite possible that they finish earlier than
the mid 2018 prediction.
Since I had over an hour with the team, we covered a lot of
infrastructure topics and there's just too much for one post. Check back
next week for part two when the discussion turns to BMW's decision to
offer free charging, but only for new i3 buyers, the future of DC
charging and BMW's long term commitment to EV infrastructure.